After the award· Explainer

You've Won the Tender. It Isn't a Contract Yet.

The email says your tender was successful. Under the Procurement Act 2023, that starts a short period in which the decision can still be questioned, challenged or even reversed. What happens between being told you've won and having a contract.

Winning a public tender usually arrives as an email: your tender was the most advantageous, and the buyer intends to award you the contract. It is tempting to tell the team, the supply chain and LinkedIn that afternoon.

Wait. Under the Procurement Act 2023, that email starts a short, formal pause before the buyer is allowed to sign. During it, the losing bidders can question or challenge the decision, and in some cases the award can still fall away. This piece explains how the pause works, and what to do with it, whether you won or lost. It is a guide, not legal advice.

From decision to contract#

The Act sets out a sequence of steps after the tenders have been assessed.

For a contract awarded through a competitive tender. Steps differ for direct awards and framework call-offs.
StepWhat happens
1. Assessment summariesEach bidder whose tender was assessed is told how its tender was assessed and, if it lost, how the winning tender was assessed (section 50(3)).
2. Contract award noticeThe buyer publishes a notice saying it intends to enter into the contract (section 50(1)).
3. Standstill periodAt least eight working days in which the contract can't be signed (section 51).
4. ContractThe buyer and the winning supplier enter into the contract.
5. Contract details noticePublished within 30 days of the contract being entered into, or 120 for light touch contracts (section 53).

Under the old rules, standstill began with a “standstill letter” to bidders. Under the Act, it begins when the contract award notice is published, and the assessment summary does the letter's job of explaining the result.

Counting the eight working days#

The mandatory standstill period is eight working days, beginning with the day the contract award notice is published. Cabinet Office guidance spells out how to count them:

  • The day of publication is working day one, even if the notice goes out late in the afternoon.
  • Weekends and bank holidays don't count, and that means bank holidays in any part of the UK. A Scottish bank holiday extends the standstill on an English contract.
  • The earliest the contract can be entered into is working day nine.

To count it for a real notice, use the standstill period calculator. It shows each day, and which bank holidays push the date back.

The buyer can set a longer standstill period in the notice, and the guidance suggests it might where a challenge is likely or the assessment summaries are long. Whatever the notice says is the period that applies.

When there isn't a standstill period#

The Act doesn't require a standstill period for every contract. The exceptions include:

  • call-off contracts awarded under a framework, whether by mini-competition or direct award;
  • light touch contracts, a category covering certain services such as some health, social and education services;
  • direct awards in cases of extreme and unavoidable urgency;
  • contracts below the procurement thresholds.

In those cases the buyer can choose to apply a voluntary standstill period, which must also be at least eight working days. If it does, the contract award notice will say so, and the same rule applies: no contract until it ends.

For framework call-offs, this means the gap between being told you've won a mini-competition and the contract can be very short.

What can happen during standstill#

The standstill period exists so that other bidders can raise concerns about the decision, or challenge it, before the contract is signed.

A challenge freezes the contract. If a supplier starts proceedings under the Act during the standstill period and the buyer is notified, the buyer may not enter into the contract. This is known as automatic suspension. It lasts until the court lifts it or the case is resolved.

The decision can be undone. While the contract hasn't been entered into, a court that finds the buyer broke the rules can set aside the award decision, order the buyer to take action, or award damages.

The buyer can change its mind. In what the guidance calls “the unlikely event” that a buyer decides not to award after all, it publishes a procurement termination notice instead of entering into the contract.

Most standstill periods pass without incident. But the point of the period is that the outcome isn't final until it ends.

Should you announce the win?#

Not yet. Three reasons to wait until the contract has actually been entered into:

  1. It might not happen. A challenge or a reversal is uncommon but possible, and retracting an announcement is worse than delaying one.
  2. The contract may forbid it. Many public contracts and tender documents include a publicity clause requiring the buyer's consent before you announce anything. Read it before you post.
  3. The buyer will publish anyway. Once the contract is signed, the buyer must publish a contract details notice, usually within 30 days. A joint announcement, with wording agreed with the buyer, usually lands better than a solo one.

Use the standstill period for things that don't depend on the contract being final. Brief the team. Plan mobilisation without committing money. Chase the documents the contract will need, such as insurance certificates, bonds and parent company guarantees. These are the ones that run on someone else's timetable. Tell key sub-contractors in confidence, and make clear that nothing is confirmed.

If you lost#

The standstill period matters more to the losing bidders than to the winner.

  • Read the assessment summary as soon as it arrives. It explains how your tender and the winning tender were assessed. It is the main evidence you have about the decision.
  • Raise questions quickly. If something in the assessment looks wrong, such as a scoring error or a criterion applied that wasn't in the documents, raise it with the buyer during standstill. A clear, specific question is often enough to get an answer, or a correction.
  • Know the clock. If you think about legal action, the Act's time limits are short: generally 30 days from when you knew, or ought to have known, about the grounds. Only proceedings started during standstill trigger the automatic suspension. Take legal advice early.

Whatever the result, the assessment summary is worth keeping. It is the most detailed feedback you will get on how buyers read your bids, and it helps the next bid/no-bid decision.